Next phase of paving project 7/30/2026

  • Writer: Muskingum Township
    Muskingum Township
  • 8 hours ago
  • 1 min read

All work will be between Chamberlain and Masonic Park

Milling

Thursday, July 30

Alden Ave

Keyser St

Lindsey Avery

1/2 of Milton Rd


Friday, July 31

Second 1/2 Milton Rd

Keeler St

Clark Dr

Walnut Dr


Paving

Monday, August 3

Keyser St

Alden Ave

Lindsey Ave

Minton Rd


Tuesday, August 4

Keeler Dr

Clark Dr

Walnut Dr

Milton Dr

Woodrow St