top of page

Post

Paving Update Week of August 3, 2026

Writer: Muskingum Township
Muskingum Township
Aug 3
1 min read

Due to water break on Alden, paving will be postponed on it until work is completed.


Weather permitting Woodrow, from Masonic to Lawton, will be paved August 4.


Starting Thursday, August 6th working on everything south of Chamberlin. (Subject to weather)


August 6 Milling

Country Club Dr

Alden Ave

Lindsey Ave

Rae Ave

Marshall Rd


August 7 Milling

Riverview Rd

Lawton Rd

Devols Dam Rd


August 10 Paving

Country Club Dr

Alden Ave

Lindsey Ave

Rae Ave

Marshall Rd


August 11 Paving

Woodrow St

Lawton Rd

Devols Dam Rd

Recent Posts

See All
2026 Fall Newsletter

Please click here to read the Fall newsletter which was also mailed to the residents.

 
 
Next phase of paving project 7/30/2026

All work will be between Chamberlain and Masonic Park Milling Thursday, July 30 Alden Ave Keyser St Lindsey Avery 1/2 of Milton Rd Friday, July 31 Second 1/2 Milton Rd Keeler St Clark Dr Walnut Dr Pav

 
 
bottom of page