Paving Update Week of August 3, 2026
- Muskingum Township
- 20 hours ago
- 1 min read
Due to water break on Alden, paving will be postponed on it until work is completed.
Weather permitting Woodrow, from Masonic to Lawton, will be paved August 4.
Starting Thursday, August 6th working on everything south of Chamberlin. (Subject to weather)
August 6 Milling
Country Club Dr
Alden Ave
Lindsey Ave
Rae Ave
Marshall Rd
August 7 Milling
Riverview Rd
Lawton Rd
Devols Dam Rd
August 10 Paving
Country Club Dr
Alden Ave
Lindsey Ave
Rae Ave
Marshall Rd
August 11 Paving
Woodrow St
Lawton Rd
Devols Dam Rd